In Maintenance › Preventive plans you create each equipment's routine:
- By calendar: every so many days, weeks or months.
- By usage: every so many kilometres or hours of the equipment's meter.
- With both, whichever comes first.
Add the checklist, the spare parts it takes and the estimated hours. Tick Stops the equipment if the machine or vehicle cannot be used while it is done.
When the work order opens
Every morning Nori checks the plans and opens the work order of the ones that are due, as far ahead as you said: the days ahead for the calendar and the ahead in km or hours for the meter. The work order brings the checklist and reserves the spare parts.
A plan has only one open work order at a time. The next one counts from when the work order is completed: the date and the meter reading at completion become the last time done.
If you do not want to wait, in Calendar use Generate work order on a plan, or Generate the due ones for all of them.
Meters
The hours of a machine linked to a work center come by themselves from the hours that section ran in Shop floor control. For vehicles, enter the odometer in Meter readings or when completing a work order. A meter only goes up: Nori does not accept a reading lower than the previous one.
Calendar
Maintenance › Calendar shows the month with the work orders on their date and, with a dashed border, the dates the plans fall on that have no work order yet. Below it is each plan with its next date or reading.
A preventive work order that stops the equipment blocks its planned window: the section shows stopped on the shop-floor board while it lasts, and the vehicle is not offered for routes or shipments that day. Schedule the vehicles' preventive work on days without a route.
Reports
- Failures and availability: per equipment, the failures, hours down, MTTR (average hours to repair), MTBF (hours running between failures) and availability.
- Cost per equipment: spare parts, labour and services of the work orders in the period. It needs the permission to see costs.
- Plan compliance: the preventive work orders due in the period, how many were done on time, late or are still pending.
The assistant also answers questions like "which equipment is down?" or "which preventive work is due this week?".
Was this guide helpful?
Related articles
Can't find something?
Tell us what you need to do and we'll get back to you. If you're already a customer, include your company's name.