The shop floor follows each production order section by section: cutting, assembly, finishing, packing or whatever sections your plant has. Each section has a tablet where operators see their work, start it and report how many pieces came out good and how many were scrapped.

1. Set up the sections

Go to Production › Setup › Work centers and create one per section:

  • Code and Name, for example CORTE · Cutting.
  • Capacity in hours per day: the hours the section can work in a day. The board uses it to warn you when there is more work than fits.
  • Cost per hour: what one hour of the section costs.
  • Resource: if you choose a production resource, the hours operators report are charged to the order as that resource, at its cost.
  • Order: the place of the section in lists and on the board.

2. Create the routing of each product

The routing says which sections a product goes through and how long it takes. Go to Production › Setup › Routings, or from the bill of materials click Routing (or Create routing if it has none yet).

  1. Choose the Product. Each product has a single routing.
  2. Add the Operations in order. For each one set the step (10, 20, 30…), the section, the name, the setup minutes (once per order) and the minutes per piece.
  3. Optionally write Instructions and a Checklist, with the points separated by semicolons or on separate lines. The operator ticks them when finishing.

Why: like the bill of materials, the routing is copied into the order when it is created. If you change the routing later, existing orders do not change. Each change raises the version, and the order shows the version it copied.

3. Set up the operators

In Production › Setup › Shop-floor operators enter each person with their Badge (code), name and a PIN. You can assign their section so they show up on the tablet, and link them to their user or to their HR employee.

Operators do not need their own user or licence: the tablet signs in with a shared user with the Shop-floor operator role, and each person identifies with their badge and PIN. That user takes one Logistics licence per tablet.

In Scrap reasons enter the reasons a piece is lost (split wood, dent, bad cut…). If there are reasons, the operator must pick one when reporting scrapped pieces.

4. Work on the tablet

  1. Sign in with the tablet user and open Production › Shop floor. Choose the section; the tablet remembers it. To change it click Change section.
  2. The operator scans or types their Badge and PIN, or taps their name. After 15 minutes without use, the tablet asks them to identify again.
  3. The queue shows the operations of released orders that go through the section, with what is Available to work on.
  4. Click Start to begin timing. Pause stops the time (lunch, shift change); Resume continues it.
  5. When done click Finish. Enter the Good pieces, the Scrapped pieces with their reason, tick the checklist and click Finish and report.

An operator works on one operation at a time. Several people can work on the same operation at once.

How work moves forward

  • A section can only work on what the previous section has already finished good. The whole order does not need to be done: if cutting delivers 4 pieces, assembly can start with those 4.
  • The operation goes through Waiting, Ready, In progress, Paused and Done.
  • Scrapped pieces do not move stock: the materials already left with the issue. They are recorded for the board and the order.
  • When the last section finishes pieces, the order shows Ready to receive. The warehouse still records the receipt from production with Receive.

Hours and cost

On the released order, the Operations section shows standard minutes against actual minutes. If there are hours to charge from sections with a resource, click Charge … h (with the pending hours): Nori creates an issue for production of the resource with the actual hours, and its cost goes into the order. When the order is closed, Nori charges any hours still pending.