Projects: plan, budget and actual cost
Create a project with its customer and manager, split it into phases and tasks, give it a budget and follow its progress, actual cost and margin without typing anything by hand.
Updated November 17, 2026
On this page
A project gathers in one place everything that happens on a job for a customer (or an internal job): its plan, its budget, people's hours, the purchases and goods issues charged to it and the invoices issued for it. It works like SAP Business One Project Management.
Create the project
- Go to Projects › Setup › Project cards and click New. You can also start from Projects › Projects › New project.
- Enter the Code and the Name.
- Choose the Type: For a customer or Internal. An internal project is not billed; it only gathers costs.
- Choose the Customer, the Manager (who approves the hours) and the Start and End dates.
- Under Invoicing choose the Billing method:
- Fixed price by milestones: you charge agreed amounts as each milestone is met.
- Time and materials: you charge approved hours at their rate and expenses with a markup.
- Enter the Contract value and the Billing item: a service item, not stocked, that gives the invoice its taxes and SAT code.
Why: the service item makes the project's invoice a regular invoice, with its taxes, its stamp and its journal entry.
The plan: phases, tasks and timeline
On the project open the Plan tab.
- Click Add phase and enter its name and dates (for example: design, installation, handover).
- In each phase click Add task. Enter its owner, dates, Planned hours, Progress and whether it is Billable.
- Click Save.
Each phase's progress comes from its tasks, weighted by planned hours. The Timeline draws each phase and task as a bar between its dates, filled by its progress; the red line marks today.
A task with hours logged cannot be removed.
The budget
On the Budget tab enter an amount per category for the whole project and for each phase:
- Materials, Labour (also in hours), Services and Other: what you expect to spend.
- Revenue: what you expect to bill.
Leave blank what you do not budget and click Save.
Actual cost comes on its own
Nobody types the actual cost. Nori takes it from what you already record, as long as the document carries the project:
| Category | Where it comes from |
|---|---|
| Materials | Goods issues, deliveries and invoices that move stock, minus returns, at the cost of their movement |
| Services | Non-stock lines of supplier invoices, minus their credit memos |
| Labour | Approved hours at their cost per hour |
| Other | Manual journal entries to cost or expense accounts with the project |
| Revenue | Invoices and debit memos minus credit memos (down payments do not count) |
The project is chosen on the document header and flows to every line; if a line belongs to another project, change it on the line. When you copy a document (order to delivery, delivery to invoice) the project travels with it. With Nori accounting, every journal entry line carries its project too.
Why: what you buy into stock is not a project cost until it leaves the warehouse for it. That way the same material never counts twice.
The Actual costs tab lists every document, movement, hour or journal entry behind the figures, with its link.
Overview and reports
The Overview tab gathers progress, approved hours against planned, what was billed, the cost, the margin and budget against actual by category.
Under Projects › Reports you have:
- Budget vs actual: budgeted and actual cost of each project, by category.
- Project profitability: billed, cost, margin and what is left to bill.
- Unbilled hours: approved, billable hours not yet on an invoice.
- Work in process: what open projects cost, what was billed and, with Nori accounting, the balance of the projects in process account.
Costs are only shown to whoever has the permission to see costs.
Roles and rates
Under Projects › Setup › Roles and rates create the roles (consultant, technician, supervisor) with their Cost per hour and Bill rate per hour. Under Rates by person link each person (user or employee) to their role and, if you want, to their own cost or rate. Hours are logged in Logging hours and billed in Project billing.
Project statuses
With Change status the project goes through Planned, Active, On hold, Completed or Cancelled. Hours are only logged on planned or active projects.
Was this guide helpful?
Related articles
Can't find something?
Tell us what you need to do and we'll get back to you. If you're already a customer, include your company's name.