Production scheduling: what runs, on which machine and when
Nori places your orders' operations into each work center's real shifts, respects maintenance and material, tells you which orders will be late, which work center is the bottleneck and when you can promise an order.
Updated November 17, 2026
On this page
Production scheduling answers three questions: what each work center does and in which order, which orders will be late and when I can promise something to a customer. Go to Production › Production scheduling.
Before you start: the plant calendar
In Production › Setup › Plant calendar tell Nori how each work center works:
- Machines: how many machines or stations work at the same time. Assembly with two benches can run two orders at once.
- Efficiency: how much of the routing's time is achieved in practice. At 80 %, a 60-minute operation takes 75.
- Shifts: each day's hours, for example
07:00-15:00or07:00-15:00, 15:00-23:00. Empty means no work that day. If you enter no shifts, the work center uses its hours per day from 8:00, Monday to Saturday. - Special days: days the plant or a work center does not work (stock count, collective vacation). Mandatory holidays from Human resources already count as closed; if a holiday is worked, add it and mark that it works.
Maintenance downtime is subtracted automatically: a scheduled preventive job and a machine down for a breakdown leave that machine without capacity while they last.
Schedule
Press Schedule and choose:
- Direction: forward starts each order as soon as possible and tells you when it ends; backward places it to end right on its due date (if it does not fit, it is scheduled forward and flagged).
- Which order goes first: by priority then due date, or by due date first.
- Group setups: orders of the same product due in the same week run together and do not repeat the machine setup.
- Include planned orders: also the ones MRP proposed and that are not released yet.
- Wait for material: an order does not start before there is stock, the purchase arrives or the component order ends. If nothing covers it, the order is flagged short of material; it is not ignored.
Nori takes each order's operations in routing sequence, with their setup and time per piece, and places them on the first free machine of the work center. Component orders are scheduled before the order that uses them. What was already done in Shop floor counts: if 30 of 50 pieces are done, only the remaining 20 are scheduled, and an operation in progress starts now.
The result is saved as a draft. Nothing changes on the floor until you publish it.
Reading the schedule
- By work center: one row per machine and one bar per operation. Hatched time is not worked and orange is maintenance. A red bar has a conflict: it overlaps another one, starts before the previous operation or starts without material.
- By order: each order with all its operations, to see at a glance how it flows.
- Load: per work center, booked hours against available hours each day or week. Green up to 85 %, amber up to 100 %, red above.
- Orders and shortages: each order with its due date, when the schedule ends it, how many days late and what material is short. Below, the bottlenecks of the next four weeks.
Move and lock
In a draft, drag an operation to another time or to another machine of the same work center. When you drop it, it is locked. Tap it to unlock or lock it.
Reschedule creates a new draft with today's shop floor progress: locked operations stay where you put them and the rest is placed around them.
Scenarios and the official schedule
Each calculation is a scenario. In Scenarios you can:
- Copy as draft to try changes without touching the original.
- Compare two scenarios: when each order ends in one and the other, how many are late and each work center's load.
- Publish the one you want as the official schedule. The previous one becomes superseded.
The official one is what the floor uses:
- The shop floor terminal sorts each work center's list by the schedule and shows each operation's slot and planned time.
- The shop floor board shows on each card the planned time against the actual one, and marks Behind schedule what should have started or ended and has not.
- The production order shows the planned and actual time on its operations.
When can I deliver?
In Production › When can I deliver?:
- A product: enter the quantity and, optionally, when the customer wants it. Nori uses free stock first and schedules the rest after everything already on the floor, with shifts, maintenance and material. It gives you the date and each operation. Nothing is saved.
- A sales order: each open line against the date promised. If the line already has a production order, it uses that order's date in the official schedule.
If the product has no routing, the date comes from its lead time.
You can also ask the assistant: "which orders are late?", "what is the bottleneck?" or "when can I deliver 40 Oak coffins?".
What it does not do
Scheduling creates no documents, moves no stock and posts no journal entries. Order costs do not change: they still come from what is issued, received and reported on the floor.